Hi,
Requirement is not clear.. You want to have the planning run in a sequence..means after planning run of plant A then planning run for plant B and then planning run for plant C to happen... then in the planning scope define the plants in the same sequence.... then planning will happen in the same sequence...
check and revert for issues if any..hope this helps.....
Thanks
Kumar