Dear Mr.Pramod,
Orders are already generated through this plan just change the basic dates.
Eg. Today ( 20.08.2013) order is generated through plan due to man power shortage you want to start working on this order on 23.08.2013 so change the basic start dates.
Or else Just set deletion flag for the order which are generated now and restart the plan.
Regards,
Harsha.